I would like to know if there is a way to create a chart or report to show the estimated time assigned to each user.
I would need to show the estimated time for all the issues that each user has assigned.
Thanks,
Thanks for you answer!
There is any way to get this report across several projects?
We have different projects and our team works on different projects each sprint.
There is a way to get that workload?
Hi Santiago,
By default (if you have time tracking enabled) JIRA has the User Workload Report which shows how much work a user has been allocated, and how long it should take. Does this help you?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.