Auto completion and start new sprint in JIRA?

M Sunil Kumar
Contributor
August 6, 2024

Hi,

Automatically close the current sprint on its last date and start a new sprint by including open issues from the previous sprint?

 

Thanks & Regards,

Sunil Kumar M.

1 answer

1 vote
Dommalapati Chandrababu Naidu
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 6, 2024

Hi @M Sunil Kumar ,

Welcome to Atlassian community!

 

Auto completing sprint is not possible in jira and there no action automation to close sprint. 

It not suggested to close a sprint automatically. when there is an active sprint you need to validate the things with team before closing it.

If you do not want to sprints we can make use of kanban. 

 

Hope this helps. 

Chandrababu

M Sunil Kumar
Contributor
August 6, 2024

Hi @Dommalapati Chandrababu Naidu 

 

Thanks for the response. Is it possible to auto start the sprint in JIRA? 

Like John Funk likes this
Dommalapati Chandrababu Naidu
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 6, 2024

It is possible to auto start and complete sprints in Data center directly from jira but it is not possible in cloud. 

 

I think it can be possible by using third party addons or REST API's but i am not sure about the process. 

 

M Sunil Kumar
Contributor
August 6, 2024

Ok, Thanks...