We have sometimes Stories or Tasks in the Kanban Backlog that during early groomings, get subtasks added to them. When the time comes to transition the Story/Task to Selected for Development, I would like for their sub-tasks to transition to the same status.
Automation feature only allows Subtask Creation.
Hi Pablo,
You can use Automation to transition the Sub-tasks when the Parent transitions.
What if the automation is working for one sub-task, but not for the other? For example, the RAD sub-task transitions to the new status, but the QC sub-task does not. (The same status is present in all sub-tasks.)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do both of the sub-tasks use the same Workflow? If not, you should look at the transitions for the QC sub-task to make sure that add-ons are not excluded in any conditions.