Is there a way to automatically move a mother issue to a status if its sub-task is moved?
Example:
Mother issue statuses - To Do (Currently set), In Progress, Done
Sub-task statuses - To Do (Currently set), In Progress, Done
So if the project manager moves a sub-task to In Progress, is there a way for the mother issue to automatically move to In Progress also?
Thanks
Hi @Andrew Q. - As Ansar says, you can do that with JMWE - it's an excellent tool and I use it myself. But it's an add-on and costs money.
Another alternative is Automation for Jira which is now free and comes with the Cloud version. You would be able to do what you want with that tool also.
Hi
If you could have JIRA Misc Workflow Extension for Cloud, then You could have this post function:
https://innovalog.atlassian.net/wiki/spaces/JMWEC/pages/94142542/Transition+parent+issue
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.