Hi 

Hope everyone doing well.

Actually, I have one scenario where I have so many subtasks 

for example 

we have 3 subtasks 

subtask 1

subtask 2

subtask 3

Now subtask 1 blocks Subtask 2 and 3 once 

Now what I want that when I changed the due date for subtask 1 

The linked issue subtasks 2 and 3 there start and due date should change automatically.

Please anybody can help me in this automation.

I am using Jira cloud

1 answer

1 accepted

2 votes
Answer accepted
Alex Koxaras -Relational-
Community Champion
January 6, 2023

@Umar Maroof 

Take the rule I gave you here https://community.atlassian.com/t5/Jira-questions/How-to-automatically-change-start-and-due-date-of-subtasks/qaq-p/2229894 and instead of having a branch with subtasks, use the linked issues and choose the appropriate link type:

linked issues.png

Umar Maroof
Contributor
January 6, 2023

@Alex Koxaras -Relational- 

Thank you so much 