Actually, I have one scenario where I have so many subtasks
for example
we have 3 subtasks
subtask 1
subtask 2
subtask 3
Now subtask 1 blocks Subtask 2 and 3 once
Now what I want that when I changed the due date for subtask 1
The linked issue subtasks 2 and 3 there start and due date should change automatically.
Please anybody can help me in this automation.
I am using Jira cloud
Take the rule I gave you here https://community.atlassian.com/t5/Jira-questions/How-to-automatically-change-start-and-due-date-of-subtasks/qaq-p/2229894 and instead of having a branch with subtasks, use the linked issues and choose the appropriate link type:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.