Hello,
I want to block is some issue change your status to "done" without all tasks "blocked by" concluded before. How can I make this automation?
Thank you!
Hello @Tools BossaBox
Welcome to the community.
Are you working with a Team Managed project or a Company Managed project?
@John Funk 's recommendation works for a Company Managed project, but does not apply to a Team Managed project.
Hi @Tools BossaBox - Welcome to the Atlassian Community!
You can put a Condition or a Validator on the transition to Done. That will determine which issues can move to Done.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.