Automation rule to link issue type to Epic already linked to a Story

Emna Elleuch
Contributor
July 9, 2024

If we supposed, i have a Story Linked to an Epic, and then i will add Task, Bugs or Dev/QA Stories and link them to the Story. 

 

how can I add an Automation Rule to link all the items: Task, Bugs and Dev/QA Stories to the same Epic linked to that Story?

 

I would like to use the Clock Work App and get the time spent for all Epic so I think everything need to be linked to that Epic, and unfortunately sometime the team forget to link do the necessary updates

Thanks in advance for your help!

1 answer

2 votes
John Funk
Community Champion
July 9, 2024

Hi Emna,

When you are linking the issues to the story, I assume that is by the issue linking functionality. So, you could create an automation rule based on an issue linked. And then add a branch for the linked issue. Under the branch Create a variable to identify the parent of the linked issue - something like {{issue.parent}}

Then use the variable to Edit the issue to update the parent field of the Bug, Task, etc. 

Emna Elleuch
Contributor
July 9, 2024

Can you please share a screen how we can add this variable ? 

 

John Funk
Community Champion
September 27, 2024

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
TAGS
AUG Leaders

Atlassian Community Events