In BigPicture added few team, team members and their respective capacity. Now In BigPicture when I try to see the resources as per team then there are many task which are showing under unassigned though the tasks are assigned to team members and most of them are done. Shouldn't the tasks should come under teams.
Please let me know how to correct it as we have a week left of the trial license for BigPicture.
thanks
Rahul
Hi Rahul, can you please give us a screen shot? Maybe one of the Issue detail in JIRA,and then one of the Gantt....I'll try to help!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
After you create the global team you have to copy that global team into your Release 3.x Program. See the 'Teams' choice in your upper right corner of your Resources screen
shot? Click that, then from the Team drop down menu, choose Copy global team to program. Then go back to the Resources view, and make sure your toggle is set to Teams, rather than Individuals, then change the view to the team name.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ericka,
Thank you for the help.
I tried as suggested but the results are same. I can still see the tasks under unassigned.
Previously program teams were created, now I tried it with both (Global and Program teams) but the nothing changed. I suppose, missing something else.
Thanks
Rahul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.