You can see I have no estimated Story points in the board here:
But you can see it is estimated and defined in the task.
Here you can see the Settings for this board, as it should work.
This isn't a bug - it's because you have Time Tracking set to "Remaining Estimate and Time Spent"
When activated, the backlog will continue to have the estimate based on your Estimation Statistic, but on the active sprint board it will utilise the field "Remaining Estimate"
If you click onto an issue and look in the issue detail view, you'll see two fields at the top - Estimation and Remaining. If you populate Remaining with a time value, it'll appear on this card.
If you want story points to show on both board views, move Time Tracking to "None"
Ste
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.