How can I get JIRA to produce the most basic scrum artifact - a burndown chart that shows the ideal burn line (in hours) as well as the actual work remaining (in hours)? This is meat and potatoes but I don't see that JIRA produces a burndown in this manner. Thanks for your help, especially if I am being a complete idiot about this. :)
Go to the Scrum board you have defined and look at the reports tab.
Plain JIRA (JIRA Core, or older JIRAs without the Agile add-on) doesn't have support for Scrum, and hence doesn't have a burndown.
As a person with Admin rights to your board, click on the 3 dots in the top right hand side (assuming a cloud version of Jira) and select Board Settings. Choose the Estimation tab and in the Estimation Statistic dropdown, choose Original Time Estimate. In the Time Tracking section, choose one of the options - we use the second one. You should then be able to go to the reporting section, choose Burndown and see exactly what you're asking for
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.