Big Picture Gannt tasks duration calculation (Start Date - End Date)

Matus Klaudiny [EXT] March 3, 2022

Hello, 

In our client's instance we would like to automatically calculate our End Date based on one of our custom fields. This field is a numbers field which is serving as a rough estimation of days that the particular task would take to finish. 

Therefore:
Start Date = Start Date
End Date = Start Date + number of days from this custom field 

Is there a way how to achieve this in Task Configuration? 

1 answer

0 votes
Anna-BigPicture
Atlassian Partner
March 4, 2022

Hi @Matus Klaudiny [EXT]

Currently, you can calculate a task end date automatically based on Time Tracking fields. Find more details in the article: BigPicture tutorial - Dates synchronization and on our wiki page.
 
Please tag me in case of further questions. 
Matus Klaudiny [EXT] March 7, 2022

Hello Anna, 

So the answer to am I able to use custom numbers field for the calculation is: 

you are not supporting it currently

Am I right? 

 

@Anna-BigPicture 

Like Anna-BigPicture likes this
Anna-BigPicture
Atlassian Partner
March 10, 2022

Hi @Matus Klaudiny [EXT]

You can map the End Date to the Original Estimate field. Then the result will be s you expect:  End Date = Start Date + a number of days from this Original Estimate Field. 
image (14).png
 
Regarding your question on the ability to map End Date to a custom numeric field, it's not possible at the moment. However, this functionality is already in our backlog. 
 
You can follow the functionality development works in the feature request ticket ONE-1727. Please note that it is best to open it in the incognito tab of your browser.