I am trying to show progress of tasks in my Gannt. I have opted for the Time Tracking original and time tracking spent fields to track the progress, but for some reason, it is not translating into an overall progress % complete for the Release.
What am I doing wrong?
Hello @Elaine Groenewald
I hope you find BigPicture a useful tool.
To display aggregated values for a Version/Release please check if you selected the type of aggregation (Sum or Sum without a parent). See my images as a reference.
If you have further questions, I will gladly answer them.
Best,
Anna