I have two projects one named "DARTMX8MP" the second is named "YOCTO" .
I have a task named "DARTMX8MP-7" which depends on the completion of "YOC-7" from YOCTO project.
I set the due date of YOC-7 tor sept. 16th. In the settings or "DARTMX8MP-7" "YOC-7" it is set the it has to be done before "DARTMX8MP-7".
However this is not reflected in BigGantt view .
Tried also "Blocked by" ...
How can this change be reflected in BigGantt view ?
Thanks,
Yair
Hi @Yair Hougui ,
External links show dependencies between tasks within the scope of different Boxes.
Unlike Internal Links they are not displayed as connectors, but as a chain icon next to the taskbar. However, you can display details like source and target task, dependency type, and mode, after clicking on a given taskbar.
Please see my image as a reference. Please notice that the screenshot was taken in the latest BigPicture 8.06 version.
Please let me know if you have further questions. I will gladly answer them.
Anna
SoftwarePlant Support