Bug status is Done, but they keep being included in the next sprint.

Ashley Freeman December 6, 2018

Hello!

I have two bugs that are marked as done and are in a state that is green in the workflow, but every time we close out an active sprint, they're moved to the next sprint, even though they're done. What could be causing this? I don't think the problem is their resolution, because I have other unresolved bugs that are not included in the next sprint.

 

Attached is a screenshot of the bug with identifying info redacted.

 

Bug.png

2 answers

1 vote
Ollie Guan
Community Champion
December 6, 2018
0 votes
PADMA KOTHAKOTA
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 7, 2018

Hi @Ashley Freeman,

 

If the status is not mapped to the right most column then the sprint take it as a undone issues and move it to the next sprint or to the backlog. Add the Done status  to the right most column in sprint board

Go to Board --> configure--> columns and add the status to the right most column