Hi,
I have an issue with how Burndown chart displaying graph, Suppose i have 1 Story point Issue under that 20 sub task these are under 1 sprint and out of that 4 have been done/resolved. when i move to burndown chart i can see that the graph still shown a straight line rather it should show that 25% of work has been done.
The graph shows completed only when all sub task under Story has been completed.
Can anyone please help me on this issue.
Thanks,
Akash
Akash, JIRA only burns up all the points of astory when it is complete
I think it is normal. Refer to the 'Definition of Done'. A task story that is at 99% is not completed.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Jira only lets you burndown points when a story is completed. In a way, that is right, since a story partially done has no real value to the customer. If you believe that even a partial story does deliver value, then split your story further.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Radu Dumitriu @Lakshmi Samudrala:Thanks for the update.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.