Below is a picture of what I see when I try to access the burnup chart. I thought the burnup chart was meant to monitor sprint progress. If so, why is it asking me to estimate items in the backlog? All the items currently in the sprint are estimated.
Have you inspected the issues in your sprint? Do they each have an original estimate? Are you using SP or Time Estimation? If you are using Classic project is your board configured for estimation?
Thanks for this. We are using story points and the board estimation statistic was set to time remaining. After setting it to Story Points it works now.
Thanks!