My sprint report for the current sprint is correctly showing that 22 points' worth of stories are in "Done."
The burnup chart for the same sprint is telling me that we have 30 points of "Completed Work."
Why the discrepancy?
Hi @Jim Strange
Please take a look at this article to see if it explains your situation:
The burn charts "are calculated as point in time, rather than the actual sprint or issues." The sprint report instead shows "the issues that have been part of the sprint at any given point in time."
Best regards,
Bill