Burnup chart disagrees with sprint report

Jim Strange
Contributor
March 27, 2019

My sprint report for the current sprint is correctly showing that 22 points' worth of stories are in "Done."

The burnup chart for the same sprint is telling me that we have 30 points of "Completed Work."

 

Why the discrepancy?

1 answer

0 votes
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 5, 2019

Hi @Jim Strange 

Please take a look at this article to see if it explains your situation:

https://confluence.atlassian.com/jirakb/burndown-reports-showing-different-story-points-than-other-reports-949763911.html 

The burn charts "are calculated as point in time, rather than the actual sprint or issues."  The sprint report instead shows "the issues that have been part of the sprint at any given point in time."

Best regards,

Bill