Based off this example, I understand how to link stories, bugs, Epics, and subtasks using Issues ID's and Parent IDs, but what about Story > Task > Subtask.
Story and Task are at the same hierarchy level. Both of those can have their own Sub-tasks. In your example you have a Sub-task as a child of a Story.
To give a Sub-task to your Task (sixth issue) you'd have another row for a Sub-task and the parent value would be 6.
Does that make sense?
Let me know if you have any more questions!