We store details of releases etc in confluence, for audit reasons we would like to freeze/baseline the jira tickets involved at the point we release.
We have jira server and scriptrunner for Jira.
What I was thinking is that it must be possible to
Then we would always have the state at closed saved to satisfy any audit.
Does it seem feasible, do I need more add-ins?
I cannot believe this is a rare requirement, is there a addin I could not find when I looked?
Hey @Chris Amos
I can think of this in a few different ways. I suppose you have a list of the required information you would need to "freeze". Would be an option to capture the details you need and add them as a comment during the transition?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.