Hello to all Jira friends here,
A month after a task was transitioned to done status in an already completed sprint, I needed to create a new subtask related to the old task. However, I couldn't assign the new sub-task to an Active Sprint. Is there anyway I can assign this kind of sub-task to an Active Sprint? If not, how you keep the connection between the tasks?
Thanks,
Roi
No. A sub-task is part of its parent, which is in a sprint already. It is nonsense to have a sub-task in a different sprint to the one it is in because it is part of a parent issue.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.