Can I estimate story on story points and sub task on original time estimates at the same time ?

Danish Qaiyoum
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 29, 2017

Hi All,

 

During planning, I want to estimate story in story points  and sub-task in original time estimates. Can I acheive this result in JIRA ? If yes then please guide me.

 

Thanks in advance.

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 29, 2017

Yes, you can.  You will probably just need to add the "time tracking" field to the screens used to create and edit the sub-tasks (the default config does not do it)

Bear in mind that if you're doing Scrum, you will only be able to work with one of these two for velocity etc, and for your set up, that one should be Story Points.