Can a Gantt chat view be created using Sprint to determine the time line? Currently I see that star

Anusha Rao September 27, 2021

Can a Gantt chat view in Big picture be created using Sprint to determine the time line?

 

Currently I see that start and end date is used, However, I would like to have a view sprintwise.

 

Kindly let me know if this is feasible.

2 answers

1 accepted

1 vote
Answer accepted
Anna-BigPicture
Atlassian Partner
September 28, 2021

Hi @Anusha Rao

The Gantt chart is a very comprehensive module so it can be used as a Roadmapping tool.
On the timeline, you can display the duration of sprints, so you can easily identify which sprint a task is in. Take a look at my image below.
image - 2021-09-28T125435.284.png
 
Moreover, you can use Sprints as a structure builder and display all tasks assigned to given sprints in your Program Box. To achieve that, first add issue type Sprint in Box Configuration >> Tasks >> Scope definition and subsequently activate Sprint builder in Box Configuration >> Tasks >> Task structure.
image - 2021-09-28T132136.570.png
image - 2021-09-28T132138.670.png
 
If you have more detailed questions, I will gladly provide you with the answer!
Best,
Anna
Anusha Rao September 28, 2021

Thank you very much for your answer Anna,

option  'Timeboxes' really helped.

However, Say a user story is assigned in current sprint , and the start and end date is defined.

If  I move the user story to next sprint, and donot  change the start and end date, then in Big Picture, the timeline doesn't change .

Isnt it better if the timeline shows the current sprint of the user story instead of the start and end date.

 

Regards,

Anusha 

Like Anna-BigPicture likes this
Anusha Rao September 28, 2021

Is there a way to do that @Anna-BigPicture.?

Like Anna-BigPicture likes this
Anna-BigPicture
Atlassian Partner
September 28, 2021
The plugin offers the option of "Precise alignment" which means that a task's period will align exactly with the box's period (e.g., Sprints). The fields mapped as start and end dates will get updated to match the boxes' start and end dates when a task is planned in one of the time boxes. 
image - 2021-09-28T163523.920.png
 
To achieve it please go to Box Configuration >> Tasks >> Scheduling >> Set alignment on lower level. See my image as a reference. 
image - 2021-09-28T163644.228.png
I hope that it answers your question. If you have any further, I am here to help. 
Like Sloan likes this
Anusha Rao September 29, 2021

Thank you so much! Is is possible to do this without the admin access? 

Like Anna-BigPicture likes this
Anna-BigPicture
Atlassian Partner
September 29, 2021

Hi @Anusha Rao

Please be advised, that only a user with a minimum Box admin security role can access and change the Scheduling. Therefore please make sure that you are added as Admin in Box Configuration >> Security. See my image as a reference.

image - 2021-09-29T105928.992.png

Like Sloan likes this
1 vote
Fabian Lim
Community Champion
September 27, 2021

Hi @Anusha Rao

The following link shows you how you can set the sprint view and put the stories and tasks under it. 

Link: https://softwareplant.com/biggantt-sprints/

Regards