Hi all,
Is it possible in Jira to block users from changing parent task status DONE (from example) until all sub-tasks are done?
I would like to manage my projects in a way that only when all subtasks are done the parent task can move to done also.
Thx
Hello,
You should add the Sub-task blocking condition to the required workflow transition (in your case the transition leading to the Done status). You can read more info on how to add a condition to workflow here:
Thx for the quick reply!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You are most welcome!
If my answer helped you, kindly accept my answer.