Can i link Jira Big Picture ( Gantt Chart ) into the Confluence Page

Kanak Gajjar
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
November 6, 2019

Hello,

 

I have created a project in my company and have also link the project with the Big Picture 

I have a few questions and want to know if that is possible.

1) Can we have the colors inputted in the Gannt chart, currently it shows only grey color

2) Possible to link the Big Picture ( Gantt Chart ) with the Confluence page which i have, where the project timlines can be auto updated in Confluence and stake holders can see the timelines as well

3) The tasks / issues which gets generated in Big Picture why cant it be in a grouped manner as in Jira they are already under a story but in Big picture they are seen as separate 

Regards,

Kanak

1 answer

0 votes
PVS
Banned
November 6, 2019

Hi @Kanak Gajjar 

 

There is no option to do this in Cloud for security reasons, unfortunately.

For server, please find the link:

Let me know if it helped!
https://wiki.softwareplant.com/display/DOCUMENTATION/Integrations#Integrations-Confluencepages

 

 

https://community.atlassian.com/t5/Confluence-questions/How-can-I-display-a-BigGantt-Chart-plug-in-for-Jira-in/qaq-p/826631

Best&thanks

PVS