Nadia Peerboom January 12, 2022

I am encountering a problem when trying to edit the start date of epics in the roadmap. When dragging the bar to change the start time (to an earlier or later date), it first displays the new start date but then jumps back to the original date after just a couple of seconds. I manager to edit it for some epics - and I do not see the same problem when editing the due date. Some of the epics are empty, while some contain user stories that are linked to sprint (with fixed start and due date according to the sprint).

Does anyone know what the problem could be? 

3 answers

0 votes
Wensi Song February 28, 2022

I have the same issue! 

0 votes
Kateryna Shevchenko January 28, 2022

I have the same problem, did you find the way how to fix? 

Nadia Peerboom February 2, 2022

Hi! We think that the problem is resolved now. One day I got an email that BigGantt had updated the start date of an issue and that made me curious if this could be the cause. Since we were not using the BigGantt project anyway, I simply deleted it and the problem was resolved. It might as well just be a coincidence, but at least it is working now for us, good luck!

Like # people like this
Kateryna Shevchenko February 3, 2022

It helped! Many thanks!)

Like Nils-Inge Engström likes this
Wensi Song February 28, 2022

Hi! How do you delete BigGantt? thanks

Enrico Del Greco
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 17, 2022

thx @Nadia Peerboom ! I resolved deleting the BigGant project

0 votes
Dave Mathijs
Community Champion
January 12, 2022

Hello @Nadia Peerboom , welcome to the Atlassian Community!

Question: Do these Epics have dependencies (finish to start f.e.) with other Epics?

Nadia Peerboom January 12, 2022

Hi! Yes, some of them have. However the same thing happens for epics that do not have any dependencies. Maybe I should also mention that we have activated advanced roadmap, but that we are currently working in (normal) roadmap within the project. 

Dave Mathijs
Community Champion
January 12, 2022

Could you share the details of such an Epic:

  • Which date picker fields are used for start and end date? Is it Start Date and Due Date?
  • Does it only happen for Epics where Stories are linked to a sprint?
  • Is your roadmap in a team-managed or company managed project?
Nadia Peerboom January 12, 2022
  • Correct, "start date" and "due date". I see the same issue when I change the start date in the field within the epic
  • No, it also happens to empty epics (i.e. no linked stories)
  • It is a company managed project 
Dave Mathijs
Community Champion
January 12, 2022

Can the Admin check whether the jira.date.picker.java.format and jira.date.picker.javascript.format in the Advanced System Settings correspond to the other date/time value settings?

System Advanced Settings Jira Date Picker.png

Nils-Inge Engström
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
January 12, 2022

What I can see it looks correct, but I also see that some change have been made ho date format is handled.

Maybe this new way of handling date format is the reason?

image.png

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
PREMIUM
TAGS
AUG Leaders

Atlassian Community Events