Hi @khushboo_puri 

You should be able to add custom fields to a Plan from the Plan's settings. It'll also tell you on that screen whether "Planning Version" is a field type which can be added to the Plan, as not all custom field types can be.

To do this:

  1. Go to your Plan, and select settings - it should be a cog icon near the Plan's name
  2. From the left-hand menu, select Custom Fields
  3. Select the "Add Custom Field" button
  4. Search & Select your required field, and add it to your Plan

Once complete, the field should be available for use, both in filtering and to be added as a column.