Can we change the sprint count of an existing increment in Easy Agile Program Board.

Anusha_Raju February 4, 2021

We have already created an increment with 5 sprints. We need to add two more sprints to the current increment. Is it possible to add more sprints to an existing increment in Easy Agile Program Board. Please let me know if there is any way to achieve this.

2 answers

1 accepted

1 vote
Answer accepted
Sean Blake {Easy Agile}
Atlassian Partner
February 7, 2021

Hi @Anusha_Raju 

You can't add more sprints to an existing increments. You could create an additional increment instead?

If this is a feature you are interested in I will pass this onto our Product team.

Kind Regards
Sean
Easy Agile

Anusha_Raju March 1, 2021

Hi Sean,

Yes I would like to pass this feature to the product team as to enable a provision to edit sprint count in an existing increment.

Thanks & Regards

Anusha

1 vote
Sudarshan
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 5, 2021

Hello @Anusha_Raju 

the Easy agile program board works based on the sprints created in your jira backlog. you can create number of sprints.

(I use it very rare, and use more of user Story maps)

as you create sprints in your projects the same will be visible in your easy agile board.

Give it a try and let me know.