Can we change the start and end date of a Project ?

Jeanne ROBERT
Contributor
August 11, 2023

Hello, 

We would like to change the date of or Software Project, but i don't find anything in the setting to do that. 

Do you know if it's possible ? and how change it ?

 

Thank you for your help !

1 answer

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Champion
August 11, 2023

Hello @Jeanne ROBERT 

Natively Jira does not support tracking a Start or End date at the project level. That information can be tracked only at the issue level.

You could find a third party product that adds functionality for tracking additional project-level attributes.

You could use a third party app that adds functionality for tracking Portfolios of projects, which would show the top level timeline for each project.

Or you could add an issue to your project that is used only to track the start and end dates for the overall project.

Utkarsh Singh
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
August 11, 2023

Hi @Jeanne ROBERT In Jira, start date and end date are tracked at issue level or at the sprint level. You can also track releases within the project but there in no feature to track the dates or the project level.