Can we have two release in a 4 week sprint

Leo Nishanth Anthony
Contributor
August 2, 2018

Hello experts. 

due to our technical reason and interdependency on multiple teams, we have to run a 4 week sprint. But sometimes this prevents the completed issue from getting released till the end of the period.

Question is can we have two release spaced at 2 weeks away in a 4 week sprint.

 

1 answer

1 accepted

1 vote
Answer accepted
Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 2, 2018

Hi Leo

Absolutely!! All that Scrum says it that you should have "releasable" chunks of code by the end of the sprint, it doesn't restrict you to that. You could release every day of a sprint if you want to.

Leo Nishanth Anthony
Contributor
August 3, 2018

Dear Levy, 

Thank you for this reply. 

BR
Leo