Cannot change/delete due date without opening edit screen

Deleted user April 7, 2020

Hi Guys,

I am having a weird issue, for some projects, I cannot change or delete the due date without opening the edit issue screen. Does anyone have an idea what might be causing that?

Thanks in advance!

1 answer

0 votes
Ste Wright
Community Champion
April 12, 2020

Hi @[deleted]

Do you mean inline editing is not available for Due Date on certain projects? Can you confirm if:

  • Inline editing is possible for other fields on the same issue where due date cannot be?
  • If there are different screens depending on the issue operation within your screen schemes - for projects where this is an issue?

I've not seen this issue before, but having different screens where due date is or is not available might be a good starting point. Make sure Due Date is on all the needed screens per issue type / issue operation.

This is assuming you have the right permissions - i.e Schedule Issues, etc.

Ste