Cannot change the team working days in the tempo team planing

Aharon Cohen March 31, 2019

hi everyone.

i'm trying to change the team working days with no success.

i went to Board -> Configure -> Working days -> i picked the desired days , and still its not effecting on the view in the timeline, for some reson its keep on showing that the working days are monday - friday, instead of sunday - thursday.

the users in the other hand are in some scheme that we configuerd to work on sunday - thursday  and it works just fine.

the add on version is Tempo Timesheetss 8.11.0

1 answer

0 votes
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 3, 2019

Hello,

I hope you are having a nice day.

The working days on the board settings of JIRA is related to the default Time tracking of JIRA and not Tempo team Planning.

To change the working days for Tempo, you can go through the steps below:

  1. Go to the team configuration page (Tempo > TEAMS more > name of team > Configuration).
  2. In the left column, click Working Days.
  3. In the team member's row, click inside the Workload Scheme field.
  4. Click again inside the Workload Scheme field, and select a workload scheme from the list.
  5. Click Update.

For more information about it, you can refer to the documentation below:

Switching types of working weeks

Let us know if this information helps.

Suggest an answer