Chain automations in jira software

Antonio Domenech Picó November 28, 2022

I would like to know how I can chain two automations so that the second one starts when the first one finishes.

Thanks in advance

1 answer

1 vote
Hamza Chundrigar
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 28, 2022

Hi @Antonio Domenech Picó 

Welcome to the community

You can allow this by checking the box next to Allow rule trigger in Rule details.

2022-11-28_13-07-21222.png

Here are some other similar community posts that discuss this in more detail:

 

Best regards,
Hamza

Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 28, 2022

Hi @Antonio Domenech Picó -- Welcome to the Atlassian Community!

Adding to Hamza's answer...

Currently, one rule cannot call another rule.  But one rule can create the conditions which trigger another rule...when you enable the option that Hamza has noted.

Please note: if your first rule has branches on more than one issue, the second rule may trigger earlier than you expect (due to the parallel and asynchronous processing of rules).  If you have concerns about this please post images of both of your rules so the community can offer suggestions.

Kind regards,
Bill

Like Amir Katz (Jira Admin) likes this