Change sprint start date in Jira 8.x

Andrey Glazkov
Contributor
February 15, 2021

I need change sprint start date after sprint was started. In Jira 7.x I could do it in "backlog" tab and everything was ok.

But in Jira 8.x changing sprint start date in "backlog" tab affect only at planned start date and not actual start date.

That's a problem because burndown chart and other charts based on actual start date.

Screenshot 2021-02-15 125505.png

Screenshot 2021-02-15 124645.png

How can I change actual start date in Jira 8.x or how can I configure burndown chart to base on planned start date?

2 answers

0 votes
C. John
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
October 5, 2021

This is a bug introduced in Jira 8.8.0. No workaround currently available. Please vote on the issue at https://jira.atlassian.com/browse/JSWSERVER-20892

0 votes
Faouzi EL YAGOUBI
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
September 30, 2021

Do you found any solution for this ?