Hi
Currently in our Jira instance the system date fields (created, resolved, etc) are displaying the date as "MM/DD/YYYY HH:MM" (Example: 09/22/2023 07:10)
And, Custom Fields (Ex: Change Start Date, Change End Date, etc) are displaying date as "dd/MMM/YYYY HH:MM" (Example: 22/Sep/2023 07:10)
We want custom fields to be displayed similar to system fields (like: 09/22/2023 07:10)
Can someone suggest how to change the format?
Thanks,
Nallu
Hi, We are on server. I think, I figured it out. Thanks.
If we go to System -> General Configuration -> Advance Settings. There is an option to change it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.