Change value for Start and End Dates in Structure

Maria Fürholzer November 20, 2019

Hi all, 

we are using JIRA (Server) in our project and are starting to use Structure, for getting Gantt-Charts created. 

We use Program Epics, Epics and Stories and estimation is done with Story Points via Sprints and Releases/ fix versions. 

Within Gantt chart Configuration Settings I use a configuration done by myself: Estimate attribute and Progress Calculation is Story Points. I also ticked allow Manual Scheduling.

First I used "Start date" as Start Date and "Resolved" as Finish Date. The Gantt-Chart bars based on these dates don't make sense to me. (see Screenshot)

I would rather like the status of the issues to be considered for Start and End Dates (eg "to be integrated" as Start Date and "Done" as End Date. So it is visible that a developer is working on the task or finished it. 

Is there any option to do so? Or am I making another mistake?

 

Thank you, 

Maria

 

1 answer

0 votes
Egor Tasa [ALM Works]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
March 24, 2020

Hi Maria,

Sorry for the late reply, this question has somehow fallen under the radar. The idea to use issue status for start and end is a good one, but currently, we can only directly accommodate the resolution date as a finish date. Potentially, you can use Script Runner to populate custom fields with status transition dates, these can then be picked up by Gantt. However, as you can see this has a lot of overhead.

Regards,
Egor Tasa

ALM Works