Jira Data Center 9.0.0: I am trying to change the default value for Priority which currently defaults to 3- Medium.
I am looking at the "Edit priority scheme" window of my priority scheme which is noted as USED BY 2 PROJECTS, the two I have thus far. I changed the Default priority to None and click the Update button. I go to create an issue in those two projects but they still default to a priority of 3 - Medium.
I re-indexed but still they do not default to None.
I logged out and back in but still they do not default to None.
Is there something else to set or associate? Just wondering what I am missing.
Hi @Boyd K
Actually it's not woring, it take the middle priority, if you have 5, it will take the 3rd.
Related to this reauest I think.
https://jira.atlassian.com/browse/JRASERVER-13048
Regards
Yeah! that's true. It takes the middle value as default.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.