If I change the 'Project Key' of a project, does that change the Key for every issue that was ever in the Project? Or does it only change the Key on issues from there on out?

Thanks for any advice.

5 answers

5 accepted

3 votes
Answer accepted
Jack Brickey
Community Champion
August 10, 2021

The prefix will change for all issues. 
abc-1234 becomes xyz-1234

2 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 10, 2021

All issues currently in the project will have their key changed (as the key is always "project I am in" - "sequence")

If however, an issue has been moved beofre the project key change, the history will report the old key of the old project, not the new.

2 votes
Answer accepted
Piotr Zadrożny _Eyzee_
Community Champion
August 10, 2021

Hi @Foxcliffe Hickory 

As already been said this will change keys for all issues on that project but you can still use old keys in searches/filters. Until you delete this projects you will not be able to reuse old key (for example you will not be able to create new project with your old key).

Please check the doc here

Best regards,

Piotr

Foxcliffe Hickory
Contributor
August 10, 2021

Thanks!

1 vote
Answer accepted
Melo
Community Champion
August 10, 2021

Hi Fox,

It changes the key for all existent issues in your project.

Thanks,

Melo

1 vote
Answer accepted
John Funk
Community Champion
August 10, 2021

Hi @Foxcliffe Hickory ,

It changes it for every issue that was ever on the Project. 