Hi ,
Upon sprint closure and selecting to move all uncompleted stories .
What is the logic for ordering the issues which moved between sprints in the new sprint BKL.
Example (to be sure above is clear) - On sprint AA - I have 3 stories which we didn`t complete --> we closed sprint and set to move all uncompleted stories to Sprint AA+1 .
Now what will be the order ? originally I thought that issues from previous sprint will move to the top of the new sprint but it wasn`t the case
Please advise
The issues all retain their global rank. If they were ranked below issues that you've moved into the new sprint before closing the old one, then you'll find they come in lower than those.
Not sur this answer is still valid... or do not understand.
We only used "Backlog order" ( all stories have the same priority).
We have some sprint created meaning current is N, we have created the sprint N+1.
We closing N => move not done story into N+1
Opening N+1
Then in new Current sprint (previous N+1), some stories remaining from N are top of board, some other in middle or at the bottom.
We would like to have all stories on top...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.