tmanai June 2, 2020

Hi,

When we want to close a sprint, Done tickets are not taken into consideration and the system offers to move them to the backlog.

The two issues that considered done is in status "Cancelled" not "Done".

Any help please?

Thanks,

SPRINT.PNG

1 answer

1 accepted

0 votes
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 2, 2020

I would guess that only one of those two status are in the last column on your board.  Reconfigure the board so that both are in the last column and try again.

tmanai June 3, 2020

It works very good. Thanks a lot

Leo Filgueira
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
June 17, 2020

Hi,

When i close Sprint, JIRA mark the issue, and this is exclude in backlog view. Which is the field used to exclude issue on the backlog view?

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
June 17, 2020

Status and sprint.