Hi everyone,
Hoping you can assist me with the following.
There are several sub-tasks that have been completed and moved to "Done" in the previous sprint; however, the associated user story (for which the sub-tasks sit) is still in progress due to other sub-tasks which are outstanding.
When I complete the sprint, the sub-tasks that are "Done" carry over to the new sprint. Is this the expected behaviour? Or is there a way I can configure the settings such that the sub-tasks that were "Done" do not carry over to the new sprint?
Many thanks!
Welcome to the Atlassian Community!
Yes, that is correct.
Sub-tasks are not really sprint items, they're only seen in the sprint display because their parent story is in the sprint and they are a piece of it.