Justin Ho October 7, 2021

At the end of the sprint, we have 12 tasks that are resolved as "done"

Screen Shot 2021-10-08 at 11.13.56 AM.png

tasks names are removed

When I click on "Complete sprint", it shows 12 are all opened still

Screen Shot 2021-10-08 at 11.16.56 AM.png 

What am I missing here?

 

2 answers

1 accepted

1 vote
Answer accepted
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 8, 2021

Are your done and closed status both in the last column on the board?

Justin Ho October 10, 2021

Oh, that fixed it! Thanks!

Susann Petzold
Contributor
January 10, 2022

edit: 

found it ;) 

0 votes
Claudio Gonzalez
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 7, 2021

Hi @Justin Ho ,

Can you verified that in yours issue? If not "Done" you need set into the workflow transition, set the "Resolution".

Screen Shot 2021-10-08 at 00.30.58.png

Justin Ho October 7, 2021

Thanks for the reply. Yes, all 12 are showing up as "Done"

 

Screen Shot 2021-10-08 at 12.35.47 PM.png