Convert sub-tasks to tasks and maintaining link

David February 26, 2018

I want to change several sub-tasks to tasks but maintain their parents i.e. continue to have some kind of link between the 2 tickets. Is it possible to do this in bulk?

e.g. I have 150 sub-tasks each of which are linked to several epics. I want to convert these sub-tasks to tasks but maintain the link to the epics.

1 answer

0 votes
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 26, 2018

No, the conversion process just changes the issue type.  You'll need to link the issues manually (or with a scripting add-on)