Converting ticket from sub-task to task removes it from the sprint

James Wardle
Contributor
November 5, 2021

Hello. We have the below scenario that I could do with some advice on.

  1. Tickets are assigned to a sprint (e.g Sprint 1)
  2. Sprint 1 starts
  3. A sub-task tickets gets converted to a Task
  4. Sprint field on ticket states Task is part of Sprint 1
  5. Burn up / Burndown chart says that tickets was added and then removed from Sprint 1
  6. History tab on Task ticket says that it was Sprint 1 -> None

It looks like converting the ticket removes the ticket from the sprint, but the Sprint field on the ticket still has it as part of Sprint 1.

Can anyone advise on what to do here?

Thanks!

 

 

1 answer

1 accepted

0 votes
Answer accepted
Bill Sheboy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
November 5, 2021

Hi @James Wardle 

That scenario seems related to these two open defects:

Please watch/vote for those to see progress.

If you believe your scenario is different and you are on a paid Jira license, please ask your site admin to submit a support ticket here: https://support.atlassian.com/contact/#/

Kind regards,
Bill

James Wardle
Contributor
November 5, 2021

Thanks @Bill Sheboy

Looks like the second one in the list matches what we're experiencing. Thanks for pointing me in the right direction.