Hi @Stany, Assuming the JIRA Admin has enabled " Time Tracking" feature and the user that has logged the original work log entry has the following permissions:
Work on Issues,
Delete Work Logs, and
Edit Work Logs project permissions
the best way to edit the work logged on a previously added work log entry is to edit that Work Log entry to the new one, thereby reflecting the accurate time for the work completed.
Here is the Atlassian documentation reference - https://confluence.atlassian.com/jiracoreserver073/logging-work-on-issues-861257349.html?_ga=2.224336594.853808868.1538510345-824083769.1520364716#LoggingWorkonanIssue-Editingaworklogentry
Hope this helps!
Thanks
Kalyani
OK, Thanks, it works indeed. However, i was confused since the 'new' forms/view do not have the tabs bar anymore. Switching back to the 'old' view did reveal them. So it works now.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.