Could i change project from kanban project to scrum project in order to manage sprint ?
Projects are Kanban or Scrum, their boards are. You can create a new Scrum board associated with the project. This will allow you to have Sprints on that board.
Adding to the answer from @Derek Fields _RightStar_
What project type are you using: company-managed or team-managed? You may find that information at the lower-left of the page expanding area.
For a company-managed project, you may add another board to use Scrum, as described.
For a team-managed project, there is only one board. You may enable sprints instead from the project features:
Kind regards,
Bill
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.