Forums

Articles
Create
cancel
Showing results for 
Search instead for 
Did you mean: 

Countdown of number of days in sprint wrong?

Sven Cipido
Contributor
August 26, 2020

Hi?

I saw that the number of days in sprint count is wrong (or I think so).
Issue with counting days for sprint.PNG

 

This screenshot is taken on 26/Aug/20 and the sprints ends on 28/Aug/20. But as you see Jira told us that there's only 1 day remaining. I suppose this should be 2 days remaining.

Is this a bug or a wrong setting on our side?

Thanks in advance

1 answer

1 accepted

0 votes
Answer accepted
Jason van Braam
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 26, 2020

Doesn't it have to do with your end time setting? 28/8/20 2 am.

Than if your screenprint is from 26/8 you have 1 full day.

Sven Cipido
Contributor
August 26, 2020

I also already thought of that.
I'm not sure, because when I changed the time beforehand, it just stays the same.

Sven Cipido
Contributor
August 26, 2020

I just tested it by changing the times. When changed Jira said 0 remaining. That was why I thought it didn't work. But then after refreshing the screen it was OK. 
Thanks.

Jason van Braam
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
August 26, 2020

I have noticed that refreshing will help sometimes :) Its the little things sometimes. Glad that it worked out.

Suggest an answer

Log in or Sign up to answer