I have a custom date field which formats to dd/MMM/yy. As you can see the text guidance below the field is wrong. How do I correct this please?

1 answer

1 accepted

0 votes
Answer accepted
Karim ABO HASHISH
Community Champion
November 22, 2022

Hello @Devtech83 

In fact, that guidance represents the custom field description. You may follow the below steps to change it. (Requires having JIRA Admin permissions)

  1. While you are logged in, type gg or . (period), this will pop the special admin menu then type custom fields.

    admin-menu-custom-fields-server.png

  2. Search for your field, from the 3 dot icon on the right select edit. 

    edit-customfield.png

    3- change the description and update so it will reflect in your screens

    change-field-description-update.png

Cheers,

Karim

Devtech83
Contributor
November 22, 2022

Thanks but unfortunately that didn't work, as you can see the default text is still there.

Screenshot 2022-11-22 at 16.53.13.png

 

 

Screenshot 2022-11-22 at 16.53.34.png

Karim ABO HASHISH
Community Champion
November 22, 2022

hi @Devtech83 

That guidance could be coming from the field configuration for the affected project.

Would you please check the field configuration for the project which have this field. The steps are illustrated below.

  1. From the project settings, open the field configuration associated to the field configuration shceme

    project-field-configuration.png


  2. Search for your field using CTRL+F and click edit

    Assignment-Date-Field-Configuration.png

  3. Make sure that the description is not empty. 

    field-description-field-configuration.png

  4. If the field description is not empty, modify it and delete the description for my first solution.
Devtech83
Contributor
November 23, 2022

Unfortunately that does not work. I have deleted the text in your 1st solution (edit custom field) and added the text into your 2nd solution (edit field description).

But I still have double text.

I tried keeping both fields empty and get the single text "Use the d/MMM/yy date format".

Karim ABO HASHISH
Community Champion
November 23, 2022

hey @Devtech83 

In this case, you will find it in the system configuration. 

  1. From the top right wheel, select system

    top-right-wheel-system.png

  2. then go to advanced settings

    system-advanced-settings.png

  3. here is your guidance

    java-date-format.png

Pro-Tip Changing the format will be applied to all projects/Date fields in your instance.

Let me know if you need further assistance.

Cheers,

Karim

Devtech83
Contributor
November 24, 2022

OK, thank you very much for your help.

Karim ABO HASHISH
Community Champion
November 24, 2022

You are most welcomed