if I setup a card A with a date and I have a subsequent card B with Dependency as " wait on" card A and I have to move my card A on the right on the timeline, in a Gantt project when I move the A the automatically moves as well. In the Planaway I see that the card B doesn't move and if I move enough the card A on the right the I only get an alert because the connections line becomes red.
Is there any way to have the card A and card B grouped together? Thank