I want to query several projects across several sprints to see if the issues we are including in a release were in the "Done" status by 12:00pm on a certain date.
For example;
status was not Done BEFORE "2020/11/30"
Is there a way to add a time component to this? I need to know if the issues were in the Done status by noon on that date.
Hi Tiffany,
Try this:
status was not Done BEFORE "2020/11/30 12:00"
How do I verify that the time is correct? I feel like the timezone in my jira instance isn't the same as my personal timezone.