I logged some time on a jira issue and I'm getting different times. See screenshots.
Any idea what causing this?
Hi @Juan Carlos
Work log history takes start date as the time you logged the issue ( which means when you have started to work )
And history takes actual time you logged the issue
You can modify the start date when you are logging work on an issue but you cannot alter the history
Let me know if you have any further queries
Thanks